| Permit Intake | Open | Permit Intake - Please clarify the licensed residential contractor and provide documentation that they have an up to date license from the Louisiana State Licensing Board for Contractors. http://www.lslbc.louisiana.gov/contractor-search/ |
| Zoning | Open | Zoning - Please submit a site plan indicating location of residence along and distance from all property lines and nearby structures. In addition, please include the location of any driveways, off-street parking spaces, and any other proposed modifications to the site. This is a double changing into a single, a current floor plan along with the proposed plan is needed. |
| Zoning | Open | Zoning - Article 21.6.T - 1. Ground-based or wall-mounted mechanical equipment (with less that 7 feet of vertical clearance) including, but not limited to, heating, ventilating, geothermal energy, and air-conditioning (HVAC) units, swimming pool equipment, and back-up electrical generators, may be located in an interior side or rear yard and shall be located at least two (2) feet from the interior side or rear property line. This two (2) foot distance shall remain open to the sky.
2. Wall-mounted mechanical equipment, with 7 feet or greater of vertical clearance, may be located in an interior side or rear yard and shall be at least 18 inches from the property line.
3. Ground-based mechanical equipment is prohibited in a front or corner side yard. Mechanical equipment setbacks in this section only apply to mechanical equipment in required interior and rear yards and do not apply if there are no yard requirements.
4. However, any existing ground-based mechanical equipment that does not comply with the location requirements as of the date of adoption of this Ordinance is considered legally conforming and may be replaced and repaired.
5. All approved ground-based mechanical equipment, including, but not limited to HVAC units, shall be screened when readily visible from the public right-of-way, excluding alleys. Screening materials may be masonry, wood, or landscape, and shall effectively screen mechanical equipment so no portion is readily visible from that public right-of-way. Color and texture of a masonry wall shall be compatile with the color and texture of the principal building on the site. If ground-based mechanical equipment is screened by an existing structure, fence or landscape, such that it is not readily visible from that public right-of-way, it will be considered to have met these requirements.
6. Ground-based mechanical equipment shall be constructed above base floor elevation (BFE), when applicable. If the equipment would be constructed so that it will be higher than a fence in the interior side yard, it may not be located within the interior side yard.
7. Any roof-mounted mechanical equipment shall be set back at least six (6) feet from any wall of the building to permit safe access to the roof and shall not be visible from the public right-of-way.
PLEASE VERIFY COMPLIANCE.
- - Alternatively, if a hardship exists, you may seek a variance from the Board of Zoning Adjustments. Contact CPC for more information at cpcinfo@nola.gov or 504-658-7033. For application materials and approval criteria please see this link: https://www.nola.gov/onestop/building/planning-project/variances/
|
| GIS Addressing | Resolved | SuppM needed to retire secondary address. |
| Plan Review | Open | PLAN REVIEW:
This project has been reviewed by Building Plan Reviewer, Dominique Scott. For email correspondence, please send to dominique.scott@nola.gov
Note: Please make sure to email the reviewer if you upload any documents on OneStop. |
| Zoning | Open | You have HVAC on your signed estimate. Zoning needs to know where you intend to install the mechanical equipment. |
| Plan Review | Open | PLAN REVIEW:
All written responses to review comments must be on a document with a letterhead, signed, and sealed by the design professional of record, or revisions must be made to the stamped plans. "Will comply" by itself will not suffice to resolve any comment. |
| Plan Review | Open | PLAN REVIEW:
Please provide a site plan, clearly showing setbacks with dimensions to all property lines as well as all existing and proposed structures on the site. |
| Plan Review | Open | PLAN REVIEW:
All plan sheets must be stamped by a professional of record, either a Louisiana-licensed architect or civil engineer as per the 2021 IRC, Section R106.1. Please revise. |
| Plan Review | Open | PLAN REVIEW:
Provide wind-borne debris protection for windows in accordance with R301.2.1.2, IRC 2021 ed. Please clarify how this will be provided. |
| Plan Review | Open | PLAN REVIEW:
Submit complete drawn details on the proposed deck/porch - materials of construction, details on proposed piers or footings, framing, joists, connectors and fasteners details, stair and handrail details, etc. |
| Plan Review | Open | PLAN REVIEW:
Approved smoke detectors shall be provided in each bedroom and outside of each separate sleeping area as required by IRC 2021, Section R314.3. Please revise. |
| Plan Review | Open | PLAN REVIEW:
Will there be any fuel-fire appliances in the dwelling? Please provide approved carbon monoxide detectors outside each separate sleeping area for any dwelling with an attached garage or fuel-fired appliances as per the IRC 2021, Section R315. |
| Plan Review | Open | PLAN REVIEW:
Where toilet rooms and bathrooms are mechanically ventilated, the ventilation equipment shall vent directly to the exterior and be installed in accordance with 2021 IRC, Section M1505.4. Please revise. |
| Plan Review | Open | PLAN REVIEW:
Will there be any windows and doors replaced? |
| Plan Review | Open | PLAN REVIEW:
Please provide the structural beam details for review. |
| Plan Review | Open | PLAN REVIEW:
Please label the intended use of all rooms on the proposed and existing floor plan. |
| Plan Review | Open | PLAN REVIEW:
Provide insulation as required by 2021 IRC, Section 402.1.3 (Note: Typ. ceiling/wall/floor values are R-38/R-13/R-13 respectively). Please revise. |
| Plan Review | Open | PLAN REVIEW:
Provide a minimum of 22’’ x 30” attic access in compliance with 2021 IRC, Sec. R807. Please revise. |
| Plan Review | Open | PLAN REVIEW:
Will the entire HVAC system be replaced? If it will be replaced, please provide Manuals S, D, and J calculations for review of the internal ductwork system. |
| Plan Review | Open | PLAN REVIEW:
Submit a signed cost estimate or contract with labor and material breakdown, and a copy of the contractor’s license certificate. The estimate or contract should:
a) include a detailed estimate of all costs including materials, labor, general conditions, contractor overhead, and profit;
b) include separate line items for any required sub-permit work (e.g. mechanical, electrical, roofing)
c) be written on business letterhead, dated, and stating the correct permit number, project address, contractor license number(s) and contact information including phone number; and
d) match the total contract amount (“Construction Value”) listed in the permit application
NOTE: All estimates or contracts shall include BOTH the Contractor’s and Owner’s signatures, printed names, titles, and date. |
| Plan Review | Open | PLAN REVIEW:
Note, full review pending on cost estimate with contractor. |