| Demolition Building Ground Area (ft²) | 2131 |
| Demolition Number of Stories | 1 |
| Demolition Cost | 142,250.00 |
| Rebuilding | Yes |
| Reason for Demolition | Current building is blighted and poses safety concerns to the neighborhood. |
| Approximate time owned by current owner | 6 months |
| Is there a redevelopment plan for the lot? | Yes |
| Proposed new use | parking for AscensionDePaul per CU received 8/12 |
| Estimated time to complete redevelopment | TBD |
| Length of time lot is anticipated to remain vacant | until building permit issued for redevelopment |
| Plan for maintaining lot between demolition and redevelopment | Yes |
| If lot will remain vacant, type of fence that will secure the lot | metal and/or wood |
| Plan for keeping lot free of trash and weeds | Yes |
| Applicant is Owner | No |
| Applicant is Lessee | No |
| Applicant is Contractor | No |
| Applicant is Architect | Yes |
| Applicant is Engineer | No |
| FEMA Flood Zone | X PROTECTED BY LEVEE,0.2 PCT ANNUAL CHANCE FLOOD HAZARD |
| Zoning | HU-MU |
| Is In Historic District | No |
| Is In Vieux Carré | No |
| Is Landmark | No |
| Council Approval Required for Demolition | No |
| Council District | B |
| Existing Building Area (ft²) | 2131 |
| Existing Use | Car Wash - Automated |
| Proposed Use | Parking Lot /Surface |
| Footprint >5,000 sq ft? | No |
| Site area > 1 Acre? | No |
| Total project sq ft > 40,000? | No |
| Will any portion of the sidewalk be repaired? | No |
| Number of Floors | 1 |
| Expected Project Completion Date | 12/31/2025 |
| Total Number of Units | 0 |
| Number of Existing Electrical Meters | 1 |
| Number of Existing Gas Meters | 0 |
| Addresses | 8020 Olive St |
| Square | 504 |
| Is this work related to Super Bowl 2025 activities? | No |